Xây dựng Trung tâm Điều khiển lưới điện tại Điện Lực Đà Nẵng

Construction of the Power Grid Control Center at Da Nang Power Company

Tên dự án

Construction of the Power Grid Control Center at Da Nang Power Company

Thời gian

2016 – 2018

Chủ đầu tư

Da Nang Power Company (PC Da Nang)

Địa điểm

Da Nang









    During the period from 2016 to 2018, My Phuong Trading Co., Ltd. collaborated with Da Nang Power Company to implement the Control Center (CC) Construction project and integrate the SCADA system, aiming to enhance automation and modernize power grid operation across the city. Da Nang.

    Project Information

    • Project Name: Construction of the Power Grid Control Center at Da Nang Power Company
    • Investor: Da Nang Power Company (PC Da Nang)
    • Location: Da Nang
    • Implementation Period: 2016 – 2018

    Phase 1 (2016):
    From August 8 to August 12, 2016, My Phuong Company conducted training and technology transfer of the Survalent SCADA software for the technical staff of PC Da Nang. Immediately after the training course, the Dispatch Department of PC Da Nang, in coordination with My Phuong Company, proceeded with the construction of the Control Center and the implementation of SCADA connectivity with 110kV and 220kV substations, as well as medium-voltage network devices, using international standard communication protocols IEC 60870-5-101/104 and DNP3.0.

    The Da Nang Power Control Center was commissioned and officially put into operation at the end of 2016. As of Q2 2018, the system had established SCADA connectivity and remote control for 11 substations (220kV–110kV), 12 RMUs, and more than 110 devices on the medium-voltage network, contributing to improved efficiency in dispatching, monitoring, and operation of the city’s power grid.

    Phase 2 (2017–2018):
    Based on the established Control Center, PC Da Nang continued to implement upgrades to the distribution network automation functions with the FLISR solution under the Distribution Network Automation Pilot Project.
    By January 10, 2018, the FLISR system had been successfully tested and officially put into operation for two medium-voltage feeders, 471 and 472 Ngu Hanh Son 220, covering 02 feeders and 05 medium-voltage circuit breakers.

    These feeders supply power to key areas connecting the city. Da Nang – Hoi An, where many critical loads are concentrated, including the Obstetrics and Pediatrics Hospital, Ngu Hanh Son District Hospital, the Ngu Hanh Son District People’s Committee, and surrounding residential areas.

    The commissioning of the FLISR system has significantly reduced outage duration, improved power supply reliability, and enhanced customer service quality.

    The project is considered a significant milestone in the roadmap for developing and scaling smart grid models, contributing to the modernization of the power system and enhancing the operational capabilities of Da Nang Power Company.