110kV, 50MVAr Capacitor Bank at Soc Son 220kV Substation
Tên dự án
Thời gian
Chủ đầu tư
Địa điểm
On April 25, 2025, My Phuong Trading Co., Ltd. (MPCo) successfully completed the acceptance and energization of the 110kV, 50MVAr capacitor bank at Soc Son 220kV Substation (Hanoi), under Package No. 3: Supply and Delivery of Primary Equipment issued by the Power Transmission Project Management Board of Vietnam.

Project for Energization of the 110kV, 50MVAr Capacitor Bank at Soc Son 220kV Substation
Project Information
- Project Name: Soc Son 220kV Substation
- Investor: Power Transmission Project Management Board – A Branch of the National Power Transmission Corporation (EVNNPT)
- Location: Soc Son District, Hanoi
- Implementation Period: November 2024 – April 2025
The capacitor bank is manufactured by Eaton’s Cooper, a brand with over 80 years of experience in the electrical equipment industry. It utilizes internally fused capacitor units of the EX-7Li type, with a rated voltage of 15kV and a capacity of 565 kVAr per unit, with a total of 120 units (50MVAr per bank).

The 110kV – 50MVAr Capacitor Bank at Nghi Son 220kV Substation Contributes to Improving Power Factor and Power Quality
The commissioning of the capacitor bank contributes to maintaining transmission grid voltage in the Northern region within permissible limits, meeting the increasing power demand of critical loads. It also enhances the stability of power supply, reduces power and energy losses, and thereby improves the operational and business efficiency of Vietnam Electricity (EVN).