On April 19, 2025, My Phuong Trading Co., Ltd. (MPCo) successfully completed the acceptance and energization of the 110kV, 50MVAr capacitor bank at Thanh Nghi 220kV Substation (Ha Nam Province), under Package No. 3: Supply and Delivery of Primary Equipment issued by the Power Transmission Project Management Board of Vietnam.

Project for Energization of the 110kV, 50MVAr Capacitor Bank at Thanh Nghi 220kV Substation
Project Information
- Project Name: Thanh Nghi 220kV Substation
- Investor: Power Transmission Project Management Board – A Branch of the National Power Transmission Corporation (EVNNPT)
- Location: Thanh Nghi Commune, Thanh Liem District, Ha Nam Province
- Implementation Period: November 2024 – April 2025
The capacitor bank is manufactured by Eaton’s Cooper, a brand with over 80 years of experience in the electrical equipment industry. It utilizes internally fused capacitor units of the EX-7Li type, with a rated voltage of 15kV and a capacity of 565 kVAr per unit, with a total of 120 units (50MVAr per bank).

Successfully Completed Another Key Power Infrastructure Project at Nghi Son 220kV Substation
The commissioning of the capacitor bank contributes to maintaining transmission grid voltage in the Northern region within permissible limits, meeting the increasing power demand of critical loads. It also enhances the stability of power supply, reduces power and energy losses, and thereby improves the operational and business efficiency of Vietnam Electricity (EVN).